Facility Production Rerouting

The facility Production Rerouting job allows you to choose a new target for fluids processed at one facility or group of facilities.

Facility Production Rerouting inputs

Note that the Reroute From field does not refer to the source of the fluids being rerouted (facilities or well manifolds), but to a single facility currently receiving fluids; these will be rerouted to the new destination facility entered under Reroute To. In the example above fluids will not be sent from Temporary Processing to Oil Processing; instead, all fluids previously going from any source to Temporary Processing will now go directly to Oil Processing.

Facility Production Rerouting does not affect fluids going directly from wells; to redirect the production of a well see Well Production Rerouting.

A facility subject to a Facility Production Rerouting job is automatically abandoned.